Project 1

Client: Weedon Developments

Location: Hemel Hempstead
Dates: Dec 2107 – April 2018

We were the Acting Principal Contractors on this project and it was one of our most complex and challenging. Our client required the groundworks for three new townhouses which sounds simple enough. However, these townhouses needed to be cut into the ground to create a basement style foundation. This had to be done on the side of a very steep incline between two existing houses which created limited access for the works to be complete.

This project took approximately four months to complete and included the following work;

  • Erect of site hoarding
  • Demolition of existing house
  • The underpinning of 2 nr adjoining properties
  • Site dig out
  • Foundations
  • RC walls
  • Substructure masonry
  • Drainage and services
  • Block & Beam Floors
  • Waterproofing
View Our Residential Development ServicesView Our Residential Development Services